SBI MANDPESHWAR
(Borivali West )
MODI SPACES.
1) 100% Casting work of 18th Slab is completed on site.
2) Shuttering and reinforcement work for 19 th floor slab is in progress on site.
3) Internal finishing work is also in progress on site like Block work, Gypsum,tiling, fixing of windows, flooring waterproofing etc.
HIRKANI SOCIETY
(Goregaon East.)
1) 8th slab (Part -1) casting work is completed
2) And 8th floor level columns reinforcement work is in progress for part -2 slab.
3) Internal finishing work like Block work, tiling, waterproofing etc is also in progress on site simultaneously.
Name of the Society: ANAND SOCIETY SANTACRUZ EAST
1)Plinth beam casting work is completed on site.
2)1st slab casting work is completed.
3) 2nd slab beams and slab bottom shuttering work is in progress.
Name of the Society: ADINATH CHSL
• RCC WORK IS IN PROGRESS ON SITE
• TOTAL 9 SLAB CAST OUT OF 22ND SLAB
• INTERNAL BLOCK WORK IS ALSO STARTED FROM FIRST HABITABLE FLOOR
• GROUND FLOOR SHOPS WORK IS ALMOST COMPLETED